M55 Westbound Resurfacing Work

We have received notification from Highways England that they will soon be commencing a resurfacing programme on the M55 westbound carriageway between
junction 1 and junction 3.

The works are due to start on Monday 4 December 2017 for two weeks.

In order to carry out the resurfacing it will be necessary to have the following traffic management, weather permitting:

  • Lane 1 will be closed for the duration of the works
  • From 8pm on Monday 4 December until 6am Tuesday 5 December - full closure of the westbound carriageway between junction 1 and junction 3 for the setting out of the traffic management.
  • From Tuesday 5 December until Sunday 10 December - from 8pm until 6am Lane 1 and Lane 2 closure (Lane 3 open).
  • From Wednesday 13 December until 18 December – full closure of the westbound carriageway between junction 1 and junction 3 each night between 8pm and 6am.

A signed diversion route will be in place during these closures.

If you require any further information regarding the scheme please contact the Highways England Customer Contact Centre by e-mail info@highwaysengland.co.uk or phone 0300 123 5000.